| SNOW MILL POND THE AREA IS UNDER CONSTRUCTION WELCOME BACK SNOW MILL POND ALL RIGHT RESERVED (C) 2009 /2010 |




FIRST STAGE OF CONSTRUCTION. SAND BAGS HAVE BEEN PLACED AROUND THE CONTROL TOWER IN ORDER TO DIVERSE THE WATER AWAY FROM THE CONSTRUCTING AREA. |
| DATE: SEPT. 4,2009 ALL THE HEAVY EQUIPMENT HAS BEEN BROUGHT IN. THE RIVER BELOW THE DAM HAS ALSO BEEN SAND BAGGED IN ORDER TO CONTROL ANY CONTAMINATED WATER. THE RETAINER WALL AS BEEN REMOVED ,THEY ARE PREPARING THE AREA IN ORDER TO SET THE FOUNDATION |
|
|

| DATE: SEPT. 26,2009 THE FOOTING AND THE NEW RETAINER WALL HAS DRIED .THE FORM'S HAVE BEEN REMOVED. THE SANDBAGS HAVE BEEN REMOVED ,FROM THE BOTTOM OF THE DAM. FILL WILL BE ADDED AND A LITTLE LANDSCAPING WILL COMPLETE THIS PROJECT. |

|